Main structural engineering: completed
Aluminum doors and windows exterior decoration project: 68% has been completed, 3-29 floor window frame installation, aluminum cladding, grille, glass railing embedded parts installation, aluminum doors and windows exterior decoration project is expected to be completed by the end of May 2021.
The second decoration project: 80% has been completed, the wall plastering is expected to be completed by the end of January 2021, and the interior and exterior wall paint is expected to be completed by the end of May 2021.
Ceiling project: 60% has been completed and is expected to be completed by the end of February 2021.
The tiling project: 45% has been completed and is expected to be completed by the end of May 2021.
Electrical and mechanical wiring engineering: 92% has been completed and is expected to be completed by the end of May 2021.
Air-conditioning project: 55% has been completed, the air-conditioning piping is expected to be completed by the end of February 2021, and the air-conditioning installation is expected to be completed on June 30, 2021.
Fine decoration: 38% has been completed, and it is expected to be on July 31, 2021.