Construction Status of Picasso City Garden in Jul. 19, 2021

A mansion with both aesthetics and life-Picasso City Garden is still standing firm in the epidemic and moving forward gradually. Now that the outer scaffolding has been removed, the exterior design with texture and local characteristics is clearly visible.
At present, the main structure has been completed, nearly 90% of other projects have been completed, and the fine decoration project has also been started.

Main structural engineering: 100% completed

Aluminum door and window exterior decoration project: 90% completed, 3-29 floor window frame installation, aluminum clad plate, grille, glass railing embedded parts installation, aluminum door and window exterior decoration.The project is expected to be completed by the end of July 2021

Secondary decoration project: 98% completed, wall plastering is expected to be completed by the end of January 2021, interior and exterior wall paint is expected to be completed by the end of July 2021

Ceiling project: 90% completed, expected to be completed in early August 2021

The tiling project: 90% has been completed and is expected to be completed in early August 2021

Electrical and mechanical wiring engineering: 95% has been completed and is expected to be completed by the end of July 2021

Air-conditioning project: 90% completed, air-conditioning piping is expected to be completed by the end of May 2021, air-conditioning installation is expected to be completed on July 30, 2021

Fine decoration: 65% has been completed, it is expected to be August 30, 2021

潔具進場
梯廳裝修工程
梯廳天花板工程
乘客電梯安裝,7月20日完成安裝
建築外觀現況
室內油漆工程
空調安裝
泳池機電配管作業
R1宴會廳空調安裝與天花板施工
G樓滿堂架作業 機電配管7月底完成
20-26F貼磚工程
20-26F貼磚工程
鷹架工程於7月20日下架完成
鋁包板骨架施工