Construction Status of Picasso City Garden on April 9, 2021
Main structural engineering: completed Aluminum doors and windows exterior decoration project: 68% has been completed, 3-29 floor window frame installation, aluminum cladding, grille, glass railing embedded parts installation, aluminum doors and windows exterior decoration project is expected to be completed by the end of May 2021. The second decoration project: 80% has been completed, the wall plastering is expected to be completed by the end of January 2021, and the interior and exterior wall paint is expected to be completed by the end of May 2021. Ceiling project: 60% has been completed and is expected to be completed by the end of February 2021. The tiling project: 45% has been completed and is expected to be completed by the end of May 2021. Electrical and mechanical wiring engineering: 92% has been completed and is expected to…